Name of the Experiment:
To Study the 2-wire DC Distribution feed at one end and calculate the various load current.
Apparatus Required:
1. Trainer kit.
2. Patch chords.
Diagram:
Theory:
Procedure:
1. Connect positive lines of S1 to T1 and common point of the G (GND terminal to G.
2. Connect voltmeter between T1 and G.
3. Connect ammeter terminals in series connection positive line of respectively.
4. Connect feeder terminal T2 to R1 through Ammeter.
5.Connect another end of R1 to common point of G.
6. Connect feeder terminal T3 to R2 through Ammeter.
7.Connect another end of R2 to common point of G.
8. Connect feeder terminal T4 to R3 through Ammeter.
9.Connect another end of R3 connect to common point of G.
10. Connect feeder terminal T5 to R4 through Ammeter.
11.Connect another end of R4 connect to common point of G.
12. Verify the connection as per the connection diagram and connection procedure.
13. Switch ON/OFF the power switch.
14. Note down the various ammeter reading and tabulate it.
15. From that find out the various potential drop between feeder terminals using voltmeter/ Mutimeter.
16. Calculate the voltage drop of feeder T2, T3, T4, T5 by using the line current I1, I2, I3, I4 and the resistance of the line.
17. Verify the measured value and calculated value.
Observation Table: –
| S. No | At Feeder Current | |||
| I2 | I3 | I4 | I5 | |
Potential drop between.
| T1 & T2 | T2 & T3 | T3 & T4 | T4 & T5 | T5 & T6 |